Timeline
BEATRICE OIL FIELD TIMELINE
To date:
1976
- MESA Petroleum Co. strikes oil in the Beatrice field
1978
- Project development approval awarded
1981
- Oil production starts, led by BNOC
1988
- BP acquires oil field and facilities from Britoil (formerly BNOC)
1996
- Talisman Energy acquires oil field and facilities from BP
2001
- 59 kilometres replacement section of oil export pipeline installed
2004
- Beatrice decommissioning programme approved by DECC in anticipation of eventual decommissioning, based on reuse of the platform complex by the Ministry of Defence
2007/8
- Two demonstrator wind turbines installed to supply power to the Beatrice facilities
2008
- Ithaca Energy takes over Beatrice facilities to aid productions at its Jacky platform, tied back to Beatrice. Talisman Energy retains eventual decommissioning liability
2012
- Joint venture created between Talisman Energy and Sinopec – Talisman Sinopec Energy UK Limited
- Ministry of Defence withdraws from reuse agreement for Beatrice
2013
- Early stage studies initiated by Talisman-Sinopec Energy UK to inform Beatrice decommissioning pre-planning
2014
- Ithaca Energy gives one year notice of intention to withdraw from Beatrice in January 2015
- Environmental and pipeline surveys commissioned by decommissioning team to inform planning
- Draft Scoping Report for the Environmental Impact Assessment published for stakeholder comment
2015
- Beatrice returns to the Talisman Sinopec (Repsol Sinopec)
- Comparative assessment of pipeline decommissioning options undertaken
- Stakeholder review of potential pipeline removal options and broader decommissioning proposals
2016
- Decision taken on timing and shape of decommissioning programme
- B&C well abandonment campaign planned and approved
2017
- Alpha well abandonment planning